Builder poured our footings 6 inches off and the fix cost $3,400
Walked the foundation layout last Tuesday morning in the Cedar Park project and noticed the back wall string line was way off from the stakes. Turns out the crew set the forms off a benchmark that had gotten knocked over by a delivery truck the day before, so the whole thing was 6 inches short on the garage side. I stopped the concrete truck before the second half of the pour, made them break out the wet forms and re-stake off a fresh control point. Ended up eating $3,400 in rework and a 4 day delay, but pouring it wrong and finding out at framing would've been way worse. Anyone else set a rule about re-checking benchmarks before every single footing pour, or do you trust the surveyor's marks?