Shoutout to the framer who suggested we order windows 4 weeks before the rough-in inspection
Our builder's timeline had them coming later, but he said the lead times were crazy and he was right. Has anyone else had a trade give you a heads-up that saved your schedule?
2 comments
Log in to join the discussion
Log In2 Comments
skylercooper7d ago
Our plumber told us to order the tankless water heater eight weeks out, which felt crazy early. It showed up with two days to spare before his install date. That kind of heads-up is pure gold.
7
young.drew6d ago
Eight weeks is a ridiculous lead time for any appliance.