Took over a 12 year old Vista system in Cleveland and the keypad wiring alone was a 3 hour fix
The old keypads in this Cleveland house used 4 wire runs with no EOL resistors, and half the zones were daisy chained through the attic. After I swapped to a newer panel and re-ran 2 homeruns, I went from chasing 6 random faults a month down to zero for the last 8 weeks. Do you guys always re-pull keypad wire on takeovers, or do you roll the dice on the existing runs?